Work is continuing on pre-slab preperation. Gravel was spread over the slab area and initial slab pouring is scheduled for this week (weather permitting). Below is a summary of last week’s progress:
- Installed under slab electrical to the electrical room.
- Roughed in restrooms.
- Poured elevator pit walls.
- Installing domestic water line.