On Sunday, March 17, 2024, we presented a Building Faith Update to the congregation in which we covered some important project milestones and discussed a number of building elements that are not part of the current project scope, but could be added back in as funds...
This week marked in important milestone in our project as the timber trusses were hoisted into our sanctuary. Seeing these massive fir timber assemblies flying through the air was an impressive and exhilerating sight! It was also a thrill to have our building...
Many people have expressed their excitement as they see the construction of the 2-story “atrium” section of our building continue to progress. Not too infrequently, however, a recurring question does pop up: “When will the timbers arrive?” As...
The second floor of the atrium/classroom section of the building has been poured, and the steel structure continues to shape the building exterior. Over the next few weeks, the exterior framing and sheathing will be installed which will provide a much clearer visual...
Not your average 2-story building… Every incremental step in the construction process so far has been really exciting to see. We have waited a long time to witness what is now actually taking place at our church property. From initial mobilization to the pouring...
Remember the structural steel… Structural steel has been a top-of-mind component of our building project for a long time. Initially, we had growing concerns over the rapidly escalating steel prices we were seeing worldwide. Then, we had to contend with unusually...
All other ground is sinking sand… The slab of the atrium/classroom section of our building has been poured, and the sanctuary foundation will be poured soon. We all know how absolutely essential a solid foundation is to the strength, integrity, and sustainable...
Work is continuing on pre-slab preperation. Gravel was spread over the slab area and initial slab pouring is scheduled for this week (weather permitting). Below is a summary of last week’s progress: Installed under slab electrical to the electrical room. Roughed...
Latest Activity from the Project Site… Check out the most recent progress captured from our onsite camera! As the project gets underway, we will be sending out regular Building Faith Bulletins by email and posting links to the bulletins on this site. They...
Our General Contractor has set up the job site trailer on the property, and several onsite coordination meetings have already taken place in preparation for the project start date. Over the next few weeks, you can expect to see much more activity as full mobilization...